Out with Deterministic Project Planning
November 11th, 2008 by HalOne of the highlights of the PMI Global Congress 2008 for me was my meeting with Greg Balestrero, CEO of PMI. On the last day of the congress Greg met with the PMI New Media Council for lunch. We had an hour-long chat. We heard what was on his mind and we shared some topics with him. Along the way we got into a conversation about standard practice and best practice. Eventually, Greg let out the "T" word. Let me back up…
The reductionist deterministic approach to planning had outlived its usefulness.
The PMI member community routinely misunderstands PMBoK® as PM methodology. It's not methodology. It is a guide to the generally accepted practices. And it is an ANSI standard. All that is meant by standard is that most people most of the time would do the actions described. It is not best practice. As the New Media Council members and Greg were discussing the usual confusion about PMBoK, one of the council members asked about featuring more best practice at the coming PMI Global Congress. Someone went on to say that we needed research into Project 2.0. It was in that conversation that Greg uttered the word "theory".
Greg said it's time we look at non-deterministic approaches to projects. I was floored. I got my composure and told him how much I appreciated his comment going on to add that the reductionist deterministic approach to planning had outlived its usefulness. But on further consideration, it's not so much that people believe that we can plan the work and work the plan, project people know that they have to be ready to respond to the always-uncertain future. It's just we use the same old (and new) tools in a way that is consistent with a reductionist deterministic approach.
Let the research begin!
What's the opposite of non-deterministic? Probabilistic? Stochastic? Should we head back to PERT? Or is Greg suggesting we leap forward to some new construct for thinking about projects? What are the tools and practices that are consistent with a non-deterministic way of planning and executing projects? How can the social Web enable altogether different practices? Is the emphasis on innovation and collaboration a passing fad? What about learning? Lean? Agile? So…let the research begin!
Related Posts
- Construction Summit 2003 — Readers Questioned A few readers asked me to comment further on my postings about Construction Summit 2003. Mostly I was not clear about m...
- Phase Planning Today Phase Planning is a key collaborative practice for establishing how a team wants to meet an upcoming milestone. Among...
- Planning is Practice for Planner-Doers I'm in the process of writing a paper with Greg Howell titled Projects, Planning, and Promising. In the paper we are se...
- Story-Telling Prepares for Uncertainty Just give me the facts. Have you said that? I have. What is this about? We operate with the illusion that we can be ...
- Simulations Can Be Learning Tools for Contractors There is never enough time to design the production system for construction, yet there is more than enough time for ma...









November 12th, 2008 at 2:17 am
project management came from codifying common mental models. deconstruction from goals into chunks of work. relationships among the chunks. using attributes of the nodes and edges to do a little math, even probabilistic math. it’s powerful stuff.
but i wonder about other ways of thinking about a big thing many people do (not calling it a project). like a political campaign, which is so amorphous and organic and emergent and social. or iterative creative works like filmmaking and software design, where the goals are approximate at best and the methods for doing work are adapted and improvised.
has the PMBoK met its natural limits? or do we want to enjoy some of PM’s benefits in areas of work where reductionist models never took hold?
November 12th, 2008 at 5:42 am
At last! More people who are starting to ‘get’ it. The PMBoK is not ‘the’ guide, it is ‘a’ guide to what most people are doing. Furthermore, it is not a methodology, simply a collection of knowledge areas which are investigated and acknowledged to one extent or another by effective and successful managers of projects.
Project management is environmentally specific - that is, the more complex, asymmetric and chaotic the environment the greater is the need for lean project management techniques. It is only in the very stable environments that rigorous project planning is possible - and how often do we come across them?
At its best the PMBoK defines those elements which must be considered, either briefly but concisely (in complex environments) or rigorously and with great detail (in stable environments). At its worst the PMBoK is a danger because some people regard it as a book of rules and procedures which must be slavishly followed. Sadly, too many of our formal education and training institutions fall into this latter category.
November 12th, 2008 at 6:52 am
Hal,
Interesting to hear that from PMI. I’ve been telling people that you have to plan for change for some time. We know from decades of research, that requirements change during product development. The rate of change is usually in the neighborhood of 25% per year. How many projects cook that number into the plan?
Planning for change means that we plan interventions to discover what the change needs to be. The problem with requirements is not unstable requirements. It is that we fail to stabilize the requirements before the end of the work. If we have not received any product changes for 6 months, we need to assume we have not looked!
All product development work involves learning. Perfect planning assumes we already know the solution. It simply is not true. Where is the learning, research, etc. in your project plan? How is that built into the needed replanning?
Bob Ferguson
November 12th, 2008 at 10:34 am
Greg, while I admire and respect him, should catch up with how programs are planned and managed in defense and space. Probabilistic cost and schedule has been mandated through DID 81650 since Jume 2005. Incorporating IMP/IMS (Integrated Master Plan / Inegrated Master Schedule) and your’re the 21st century. Heavy construction does the same using in many firms.
The next step is Earned Schedule integrated with Eraned Value. See PMI College of Performance Management’s, Measurement News for a detailed set of papers. Add to that probabilistic portfolio management of projects inside programs, Markov Chains using Monte Carlo forecasting of future performance, and you’ll be caught up with the current state of the art for cost modeling and schedule impact analsyis.
Glen B. Alleman
VP, Program Planning and Control
Aerospace and Defense
Denver, Colorado
November 23rd, 2008 at 11:00 pm
Hal, I thought having drinks with me in Denver was the highlight of your conference.
PMBoK has a set of process groups that are addressed in every project, intentionally or not. The Program and Portfolio Standards have related and interdependent process groups as well. Each project, like Glen’s development of a missle system, or the evolving creation of a web based business application address these process groups. I just don’t think we are going to get away from the capabilities of planning, communicating, staffing, procurement, quality, etc.
The issue is to figure out the appropriate trade-off between perfect planning versus organizational learning and progressive elaboration. The process groups may not even be all inclusive. In OPM3 we included a set of Organizational Enablers that could be addressed as well. But it is unreasonable to purposefully address all of these processes for many projects, so how do we limit our focus and investment into the project delivery capability to the smallest amount of effort neccessary to optimize the delivery of the project?
We keep getting caught up in the “How Trap” of historical implementations of these processes and not addressing the outcome gaps. Where we need to innovate is to figure out for each project how we implement the best practices to achieve the outcomes for that particular project. How do we bring in new practices and organizational/social constructs to continue to improve our ability to deliver projects? None of these questions are outside of the scope the PMI standards. In fact, if we can raise the conversation above the historical implementation of the process groups the standards provide a robust structure for the conversation.