Reframe Your Role for Lean Project Delivery

December 31st, 2003 by Hal

I received this email today. As I prepared a reply, I decided to share it with readers of this weblog. I started answering with the mechanics of delivering projects on a lean basis, but then it occurred to me that one needs to see their role differently to deliver projects with far less waste, higher schedule and cost reliability, and so much safer.

Hi Hal,

Please help me understand:

The CM needs an approach for bringing the interests of the specialists into alignment with the promises to the customer.

Our role in construction projects is either general contractor or construction manager (CM). We plan our projects using master CPM schedules and two-week look-ahead schedules for site activities. Typically we do not self-perform any work. How do you apply the Last Planner™ and the "pull principle" in such an environment?

Bosko

Great question. As CM you are responsible for the completion of your promises to the customer. Sub contracting doesn't shift that responsibility. You are still responsible. But how do you carry out that responsibility?

Normally, a CM hires numerous Subs to perform specialty roles. These Subs interact with each other to produce the finished spaces. Each Sub naturally acts in their own interests seeking to optimize their use of their labor, equipment, and materials. This local optimization of resources leads to an overall reduction in the productivity, risk to schedule performance, and higher costs. The CM needs an approach for bringing the interests of the specialists into alignment with the promises to the customer.

The approach has three steps:

  1. Backward schedule just that work that adds value for the client. Produce this reverse phase schedule in conversation with the primary Subs on your project.
  2. On a six-week look-ahead basis prepare the work, wherewithal, and the circumstances for completing the work on the reverse phase schedule so that each task can be started and completed without interruption. Continue to review and make-ready the work adding a new week from the schedule each week.
  3. Have crew leaders (last planners) have public planning conversations where they promise the completion of only the work that has been prepared (ready). The weekly work plan (WWP) is the sum of the promised tasks. Use the WWP to guide what is done on a daily basis. Also use it to measure how you are performing and to learn from planning failures.

Your aim is to have tasks completed as promised. As CM you have a project manager and site superintendent for the project. Their roles shift from controlling (after-the-fact monitoring) and motivating (carrot and stick) to engaged planning, preparing, and navigating with those people performing the work. The essence of the your work as CM is to see that performers are in a position to be successful with their efforts.

Lean projects require more conversation, more engagement, and more teamwork. Your role is to be the leader that brings all that about.

Related Posts

Social Bookmarking
Add to: Folkd Add to: Linkarena Add to: Digg Add to: Del.icio.us Add to: Reddit Add to: Simpy Add to: StumbleUpon Add to: Slashdot Add to: Netscape Add to: Furl Add to: Yahoo Add to: Spurl Add to: Google Add to: Blinklist Add to: Blogmarks Add to: Diigo Add to: Technorati Add to: Newsvine Add to: Blinkbits Add to: Ma.Gnolia Add to: Smarking Add to: Netvouz Information

2 Responses to “Reframe Your Role for Lean Project Delivery”

  1. Frank Patrick Says:

    Ah yes –

    CM/PM as facilitator.

    Happy New Year, Hal!

  2. Gary Kuhn Says:

    Hal, how could i have been so lucky as to start my New Year off with such a straight forward synopsis of the beauty of Lean. Trust with conversation focused on the Customer all accomplished by just meeting commitments. Baby oh Baby!

    Happy New Year!

    gary

Comment On This

Note: This post is over 4 years old. You may want to check later in this blog to see if there is new information relevant to your comment.